Kenyans to pay more over Ketraco delayed projects

Pylons from the 220KV Suswa substation in Narok County.



Photo credit: File | Nation Media Group

What you need to know:

  • The delays in clearing the amount have been attributed to lack of budgetary allocation from the National Treasury and long talks between land owners, the company and various county governments.
  • Delays in compensating project affected persons may expose the government to legal suits, cost escalations and project delays.

A number of court cases involving wayleave acquisition and contractor claims as well as some land owners who cannot be traced, means that State agency will always have its hands full

Auditor-General Nancy Gathungu has sounded the alarm that Kenya Electricity Transmission Company (Ketraco) may be exposed to unforeseen project cost overruns due to ongoing court cases, wayleave acquisition and contractors claims.