Revealed: The Italian conditional grant holding up Sh2bn dam project in Baringo

Kirandich dam Baringo

Rift Valley Water Services Board officials, county leaders and consultants during a pre-tendering site visit at Kirandich Dam in Baringo County on February 24, 2015.
 

Photo credit: File | Nation Media Group

What you need to know:

  • According to the CS, the biggest challenge is that the contractor was identified by the Italian government, which is also the financier of the project.

Labour Cabinet Secretary Simon Chelugui has blamed the stalling of the Sh2 billion Kirandich dam in Baringo on an inefficient contractor, whom he said the government could not sack because of a conditional grant clause in the contract.

According to the CS, the biggest challenge is that the contractor was identified by the Italian government, which is also the financier of the project and the government could not get a different company because the funding is a conditional grant.