Construction machines at the site of the stalled multi-billion shillings Itare dam in Kuresoi North, Nakuru County on October 8, 2020.

|

Sh30bn Itare dam now no more than a grazing field

What you need to know:

  • Last December, the DCI launched an inquiry into the scandal and summoned several former board members of Rift Valley Water Works Development Agency.
  • Also summoned were top government officials in the Ministry of Water and Sanitation over alleged corruption in the project.
  • Angry residents who leased some of their land to the company to set up temporary working stations now want the insolvent company to remove its machinery.

The messy story of the stalled Sh30 billion Itare dam is well illustrated by the torn Kenyan flag flying at the abandoned construction site in Kuresoi North, Nakuru County.   

The flag of the Italian contractor, CMC di Ravenna, and that of Italy flying besides the national flag are equally tattered.